Star After the concrete has cured underwater, let the water dry away.

After 4 weeks you do not need water over the slab.  Stop the daily topping up with the water and let evaporation happen until the water has gone.  During the drying it is good to take photos every day to give you a map of where the high spots are.

Site Water With Two High Spots

Site Slab Drying End July 23 

Site Slab Drying Mid July 25

Site Slab Drying End July 25

Site Slab Drying Mid July 26 

Site Slab Drying End July 26 

Site Slab Drying End July 27 

Site Slab Drying Start July 29

Site Slab Dried

 

 

*