Header
Carnation Construction
Contact Dave
Carnation

Build Sequence

Star Full set of build site photos in chronological sequence.

House dite before starting clearing

Tree clearing nearly done

Tractor on site

Reference ditch on site

Top soil being removed

Top soil removed

Excavator starting

Excavator tree stump moving

Excavator digging in slope

Excavator western path in

Excavator end of day 3

Excavator end of day 4 from mound

Excavator danger sign

Excavation finished

Site - Batterboards set

Site From U

Site Waiting Along To South

Site Waiting Ladder

Site Green Mound

Site Digger For Septic

Site With Excavator And Dozer

Site Under Excavator Arm

Site With Deer

Site Lamppost Shed

Site Ready For Footing Excavation

Footing Excavation 07 Digging To Underslab Level

Footing Excavation From North East Above

Footing Excavation 304

Footing Excavation 314

Site Rock Still Burning

Site Rock Burn

Site Rock Burn Above

Site House Drain Pipe Above Pile

Site House Drain Pipe Looking East

Site Last Rock Burn

Site Footings Dug With Pipes

Site Form-A-Drain Stacked

Site Form-A-Drain Temp Placed

Site Jack Hammering Dusk

Site With Form-A-Drain Cut To Length

Site All Lower Form-A-Drain

Site Wood Spacers On Form-A-Drain

Site First Sock On Form-A-Drain

Site Geofabric Outside Started

Site Crushed Rock Geofabric

Site Cutting Inner Upper Form-A-Drain

Site Two Lots Of Upper Inner Form-A-Drain

Site Upper Inner Form-A-Drain Done

Site Injectors Done

Site Deck Legs Started

Site Deck Legs West Started

Site First Deck Leg Formed

Site Deck Columns Five Started

Site Colmn Location Spacers

Site Deck Leg Spacers

Site Deck Columns Stacked

Site Footings All West Columns

Site Outer Upper Form-A-Drain Started

Site All West Column Footings

Site Upper Outer Form-A-Drain Part Done

Site Outer Form-A-Drain Eps Started

Site Eps Outer And Geofabric

Site More Geofabric Eps

Site Eps Form-A-Drain Done

Site With Crushed Rock North Portico

Site Bracing Round Outside Done

Site Bracing Done Starting Outside Rock

Site Extra Bracing Crushed Rock Backfill

Site First Membrane Night

Site Crushed Rock All Slab Areas

Site Ready For First Membrane

Site First Membrane Being Installed

Site First Membrane With Some Eps

Site Outside Footing Eps Some Inner

Site Started First Eps 2in Over Slab

Site Second 2in Slab Eps Done East

Site 2nd Slab Layer Eps Almost Done

Site Last Foundation Eps Stacked Ready

Site Nearly Ready For Water Membrane

Site Water Membrane Initial Fitting

Site Starting Protection Eps

Site Gluing Eps Protection

Site Protection Eps 1in Done

Site Starting Toughliner Protection

Site Snow In Lined Footings

Site Some Toughliner

Site Bit More Protection Sheeting

Site ToughLiner Protection Getting Done

Site Protection ToughLiner Done

Site Protection ToughLiner Snow

Site Some Stirrup Assemblies Stacked

Site Rebar Stirrup Assemblies Built Stacked

Site Rebar Horiz Laid Out Starting

Site With Some Rebar In Footings

Site Rebar Stirrup Assemblies First In Position

Site East Stirrup Assemblies In Trench

Site Stirrup Assemblies East Underway Night

Site Wood Blocks On Slab Area

Site East Ext Stirrups In Trench

Site Stirrups In Trenches North Portico Started

Site North Side Stirrup Assemblies In Trenches

Site Stirrup Assemblies To West Side

Site East West Stirrup Assemblies In Trench

Site West Internal Trench Stirrups

Site Started South Portico Stirrup Assemblies

Site All Footing Rebar Stirrups Done

Site Some Foundation Goove Planks

Site Nearly Done With Groove Planks Etc

Site Foundation Groove Planks All Done

Site Started Slab Rebar First Layer

Site Half Done First Rebar Layer Slab

Site Last Slab First Layer Rebar

Site Slab First Layer Done

Site Part Way Upper Slab Rebar

Site Almost Done With Slab Foundation Rebar

Site Ready For Foundation Rebar Inspection

Site Foundation Rebar All Done

Site Column Bracing Vacing

000_SiteReadyToDoConcretePour

010_SiteConcreteFoundationPumpTruckReady

020_SiteConcreteFoundationFirstTruckArrives

030_SiteConcreteFoundationStartingFootingPour

040_SiteConcreteFoundationFixingPumpTruck

050_SiteConcreteFoundationInternalFootingPour

060_SiteConcreteFoundationEastFootingPour

070_SiteConcreteFoundationFootingsNorthPortico

080_SiteConcreteFoundationPumpingWestFooting

081_SiteFinishedPouringFootings

090_SiteConcreteFoundationRemovingTrenchCrossWood

100_SiteConcreteFoundationFillingWestSouthDeckColumn

110_SiteConcreteFoundationWalkwaysGone

120_SiteConcreteFoundationStartingSlabPump

130_SiteConcreteFoundationPumpingFirstSlabArea

140_SiteConcreteFoundationHalfWayThroughSlab

141_SitePumpingConcreteSlabMiddle

150_SiteConcreteFoundationPumpingToLastSlabArea

160_SiteConcreteFoundationLastSlabAreaFilling

170_SiteConcreteFoundationLettingAirOutSlabMembrane

180_SiteConcreteFoundationLastBitOfSlabLeveling

190_SiteConcreteFoundationFillingWestNorthDeckColumn

200_SiteConcreteFoundationFillingEastSouthPorticoDeckColumn

210_SiteConcreteFoundationFillingEastSouthDeckColumn

220_SiteConcreteFoundationFillingEastMiddleDeckColumn

230_SiteSlabFinishingNearlyFinished

Site Slab Flooded To Cure

Site Water With Two High Spots

Site Slab Drying End July 23

Site Slab Drying Mid July 25

Site Slab Drying End July 25

Site Slab Drying Mid July 26

Site Slab Drying End July 26

Site Slab Drying End July 27

Site Slab Drying Start July 29

Site Slab Dried

Site Key Notch Planks Removed

Site Slab No Groove Planks Cleaned

Site Slab Tree Eclipse Patterns

Site First Nailed Kickers

Site First Two Verticals Installed

Site Verticals North West

Site Western Basement Verticals

Site More Kickers

Site Starting Basement Walls North Portico

Site North Portico Vertical Batons

Site First Internal Verticals North

Site North Portico Has Mezz Planks

Site North Portico With Temp Mezz Roof

Site Verticals North East Started

Site Eastern Vertical Batons

Site Started Long Internal Wall

Site First Ceiling Beam On Site

Site Night Lots Of Verticals

Site Horizontal Beam Support Center

Site About To Do First Beam

Site First Five Ceiling Beams

Site First Ceiling Eps Blocks

Site Ceiling Eps With Plastic Tarp

Site Started First Internal Walls

Site Eps Blocks Over Internal Center

Site Polyethylene Over Center

Site Black Sheet Roof Center Cover

Site Wall Basement Eps North West

Site Eps 6in North Portico Start

Site Started North East Eps 6in

Site Bottom Eps East Side

Site First Eps Layer South Portico

Site Eps 6in 2nd Layer On South Portico

Site Eps 6in Started South 3rd Row

Site 6in Eps 3rd Row Nearing Done

3rd Row 6in Eps West

Site Eps East Eps Done Both Layers

Site Started Mezz East Room

Site East Room Ready For Beams

Site Many Floor Beams East Side

Site Lots Eps Flooring East Side 

Site Stair Wood Cap 

Site East Middle Covered In Plastic

 

Site Snow Over Plastic Roof 

Site Lots Of Snow 

Site Plastic Over West Too 

Site Plastic Over West Too 

Site Temporary Roofing Etc

Site Internal Ceiling Beams 

Site Before Window Bucking Fitted 

Site Before Window Bucking Fitted 2 

Site Before Window Bucking Fitted 3 

Site Snowy Basement Roof 

Site Snowy Basement Roof 2 

Site Poly Over Some Planks 

Site Poly With Old Bridge 

House Inside General View Looking Up 

House Inside General View Looking Up 2 

House Inside General View Wood 

House Inside General View Wood 2 

Site External Extended Batons Fitted 

Site Roof Polyethylene Removed 

Site With Batons Viewed From South West 

 

*